Dependencies and Scheduling

Two independent layers decide when a kernel runs on an Ascend NPU.

  1. The dependency graph says what must happen before what. It is built while the orchestration program runs, from tensor arguments and from edges you declare. Get it wrong and results are wrong — usually intermittently.
  2. The runtime scheduler picks, among all orders the graph permits, when each task is actually issued to a core. Get it wrong and results are right but late.

Most "why is this kernel wrong" answers live in the first layer, and most "why is there a 4 µs hole in my swimlane" answers live in the second. This guide builds both from the ground up, shows which artifact proves which claim, and ends with the loop that turns those artifacts into a shorter schedule.

The authoritative references are upstream: Tasks and Ordering for the dependency model and the keywords, and the simpler runtime docs for what the scheduler does with them. This page is the pypto-lib view — the mechanism as it appears in our models and our capture artifacts, plus the failures this repository has actually hit.

The unit of scheduling is a task

A task is one dispatch. The runtime never executes an orchestration function statement by statement; it builds a graph of tasks and runs whatever is ready.

Four spellings produce a task, and they produce only two shapes:

Spelling Available in Shape
with pl.at(level=..., name_hint=...) as tid: @pl.jit, @pl.function One task
result, tid = pl.submit(self.kernel, ...) @pl.program classes One task
with pl.spmd(n, ...) as tid: @pl.jit, @pl.function One task, n logical blocks
result, tid = pl.spmd_submit(self.kernel, ..., core_num=n) @pl.program classes One task, n logical blocks

Two properties follow, and both matter downstream:

  • A mixed cube+vector region is still one task. pl.at carrying both a pl.matmul and the vector op consuming it dispatches as a single task with up to three active subslots — [AIC, AIV0, AIV1] — that complete independently and retire together. It is one node in the graph, one row in deps.json, and several physical rows in a swimlane.
  • An SPMD launch is still one task. pl.spmd(n) is one scheduling unit fanned out over n logical blocks. It carries one TaskId, so a consumer waits on the whole fan-out, not on a block. Blocks are dispatched individually — with more blocks than cores the launch proceeds in waves — unless sync_start=True forces an atomic all-or-nothing launch.

Each task also carries a resource shape — MIX (a cluster of 1 AIC + 2 AIV), AIC, or AIV — derived from its active subslots. The shape decides which ready queue it enters and which cores can take it. A task never waits on a core it could not have used.

Statement order expresses nothing. Two dispatches written one after the other are ordered only if something says so: a buffer overlap the runtime can see, or an edge you declared. Source adjacency is not that something.

How an edge comes to exist

There are exactly two mechanisms, and they compose:

final wait set  =  TensorMap-inferred edges  ∪  declared deps=

TensorMap inference

The orchestrator keeps a map from tensor memory regions to the task that last wrote them. On every submit it does three things with the task's arguments:

Step Applies to Effect
Creator retention Every tensor argument, any direction Edge on the task that created that tensor
Producer lookup In / InOut Edge on the registered producer of any overlapping region
Producer registration Out / InOut This task becomes the registered producer

So parameter directions are not documentation — they are the input to dependency inference. Declaring an InOut buffer as Out tells the runtime that nothing needs to finish before this task writes it.

Which hazards that covers:

Hazard Tracked Why
RAW — read after write Yes The reader looks up the current writer and takes an edge
WAW — write after write Yes The new writer takes an edge on the prior writer, then replaces it
WAR — write after read No A writer would have to find every in-flight reader; that is a per-write walk over a reader set on the orchestration hot path

WAR being untracked is a deliberate runtime trade-off (WAR anti-dependencies), not a defect. When a pure reader must finish before a later overwrite, that edge is yours to declare — and declare it with deps= on the writer rather than by promoting the reader to InOut, which makes the reader a writer and serializes it against every other reader of that buffer.

The overlap test works on buffer regions and is conservative: a region it cannot prove disjoint is treated as overlapping. That is where false serialization comes from — most often a loop whose iterations write disjoint slices of one output but look to the map like one buffer.

Declared edges

Bind a task's TaskId and name it later:

with pl.at(level=pl.Level.CORE_GROUP, name_hint="producer") as first:
    ...
with pl.at(level=pl.Level.CORE_GROUP, name_hint="consumer", deps=[first]) as second:
    ...

Three shapes worth knowing:

  • Fan-in through an array. One TaskId names one task. To wait on a loop's worth of producers, collect them into a pl.array of pl.TASK_ID and pass the array — or the per-index list, which is what models/qwen3_14b/decode_fwd.py relies on when the array is hoisted across a scope boundary.
  • A join with no work. pl.system.task_dummy(deps=[...]) returns a TaskId that collapses several producers into one handle.
  • deps= needs the as form. with pl.spmd(n): and for i in pl.spmd(n): run the same work without naming it and reject deps= outright.

Declared edges are not tied to manual scope. They compose with inference, so one deps= inside an ordinary auto scope is the precision tool for the one edge the inference could not reach.

Turning inference off

Four opt-outs, from narrowest to widest. Each is an assertion the compiler cannot check:

Construct Scope of the claim Used in this repo
pl.at(..., no_dep_args=[t]) One tensor, one task the gate_up_dual_proj scope in models/qwen3_14b/decode_layer_a8w8.py
pl.no_dep(t) at a call argument One tensor, one task (@pl.program form) —
pl.create_tensor(..., manual_dep=True) One tensor, its whole lifetime post_ffn in models/deepseek_v4_pro/moe.py
with pl.manual_scope(): Every task in the region _decode_layer in models/qwen3_14b/decode_fwd.py

Prefer the narrowest one that expresses the claim. manual_scope says "I own the entire graph here" — inside it the runtime skips creator retention, producer lookup and producer registration alike, so every edge in the region is one you wrote, including the ones that used to be correct for free.

What this looks like in deps.json

Every edge records where it came from, which makes the mechanism directly observable:

source Meaning
creator Creator retention — the task that allocated the tensor
tensormap An overlap lookup hit; carries overlap: covered \| other and both slice geometries
explicit A declared deps= edge; arg is -1 because it belongs to no argument slot

An edge you expected but cannot find in deps.json does not exist at run time.

What happens at run time

Two AICPU roles run concurrently. On a2a3 the AICPU has four threads: one orchestrator and three schedulers.

The orchestrator thread executes the orchestration program and submits tasks. Per submit it allocates a task-ring slot and heap space for outputs, copies parameters, performs the TensorMap lookup and insert, records the producer set, wires fanout edges, and publishes the task to a ready queue if nothing is outstanding.

The scheduler threads each own a share of the cores and run a two-phase loop: drain completions, then dispatch. Completion polls each core's COND register for FIN, aggregates the task's subslots, and walks the finished task's fanout list incrementing each consumer's released-producer count — the consumer whose producers are all released moves to a ready queue. Dispatch pops a ready task whose resource shape matches an available core, writes a dispatch payload, and signals the core.

That gives one task the following timeline, and every timestamp in a level-4 capture is a point on it:

 submit ──► ready ──► dispatch ──► start ──► end ──► finish ──► consumed
    │         │          │           │        │        │           │
 orch      every      payload      core     kernel   AICPU     fanout
 thread   producer    written    picks it   returns  sees FIN  released,
          FIN'd      to a core      up                         slot freed

An early-dispatched task takes the same path with dispatch moved ahead of ready: the payload is staged on a gated core and released by a doorbell when the last producer finishes.

The four timestamps a swimlane record carries:

Field Stamped by Means
dispatch_time_us AICPU The scheduler handed this block to a core
start_time_us AICore The core began executing the kernel
end_time_us AICore The kernel returned
finish_time_us AICPU The scheduler observed FIN and can release consumers

end → finish is FIN detection latency, not compute. A consumer becomes ready at its last producer's finish, not its end.

Queues and their order

Ready work is partitioned by resource shape, and each shape has a normal lane and a speculative lane:

Source Regular lanes sync_start lane
Normal (all producers done) ready_queues[MIX\|AIC\|AIV] ready_sync_queues[MIX\|AIC\|AIV]
Early (speculative pre-stage) early_dispatch_queues[MIX\|AIC\|AIV] early_sync_start_queue

Within a source the order is sync_start ▸ MIX ▸ AIC/AIV, and per shape idle cores before busy ones (a busy core can take a gated pending slot, promoted on completion). Across sources, normal strictly precedes early — speculative work runs only once both normal lanes are empty. A ready task therefore never loses a core to a speculative one.

Back-pressure

The orchestrator can outrun the scheduler, so submission blocks when the ring holding task slots, output heap bytes, or dependency-list entries is full. It resumes when the scheduler retires tasks and advances that ring's watermark.

This is ordinary flow control until it becomes a deadlock: a task's fanout count includes a reference from its owning runtime scope, released only when scope_end() runs — and scope_end() is called by the orchestrator, the very thread blocked waiting for space. A scope that submits more tasks than its ring's window can hold therefore cannot drain itself. The runtime detects the condition and exits with an orch_error_code naming which resource wedged.

Sizing the rings, placing scopes to shorten intermediate-tensor lifetime, and reading the per-scope peaks are their own topic — see Ring Heap and Scope Stats.

Observing it

None of the above is inferable from a kernel's source. Every claim in the rest of this page — which edge exists, when a task was dispatched, what a gap was waiting for — is settled by two artifacts and their join.

The artifacts

File Produced by Carries
deps.json --enable-dep-gen The task graph: tasks, kernel_ids, block_num, early_dispatch, annotated edges
chip_swimlane_records.json --enable-chip-swimlane Per-task timing and scheduler/orchestrator phases; no edges
name_map*.json Compile Callable id → source name
dispatch_program.json Compile Which program a dispatch directory belongs to
merged_swimlane*.json swimlane_converter The two joined, for Perfetto

Timing and topology are deliberately separate: per-task fanout on the device hot path would cost a ~1 KB GM store and a linked-list walk per task. The converter joins them offline, which also means one deps.json can serve many timing runs of the same topology.

Capture levels

Level Adds
1 AICore start / end per task
2 + AICPU dispatch / finish
3 + scheduler phase records
4 + orchestrator phase records

Anything that reasons about dispatch — gap attribution, early-dispatch proof — needs level 4. Note this is the chip swimlane's perf level; it is unrelated to the runtime hierarchy's L4 worker level.

Every entry across models/ and examples/ declares the flag the same way:

parser.add_argument("--enable-chip-swimlane", type=int, nargs="?", const=1, default=0, choices=range(5))

So a bare --enable-chip-swimlane means level 1 everywhere, every level through 4 is accepted everywhere, and level 4 is always requested explicitly as --enable-chip-swimlane 4. Declare it this way in a new entry too — a store_true flag cannot express a level, and its True silently binds to the most expensive capture.

Identity chain

Runtime task IDs are capture-local — they are execution instances, not source identifiers, and they do not survive a rebuild. To get from a swimlane row back to a line of Python:

dispatch_program.json
  → next_levels/<program>/kernel_config.py
  → name_map*.json :: callable_id_to_name
  → deps.json :: tasks[task_id].kernel_ids
  → source name_hint or submitted callee

A MIX task maps to more than one callable name — check every active kernel_ids slot. Compiler suffixes such as _0 can be inlined copies of one shared name_hint, so one source site may own several runtime occurrences.

Validating a capture before trusting it

Join the streams with swimlane_converter.read_perf_data(); the raw file holds separate cycle-domain streams that must not be joined by hand. Then require:

  • chip_swimlane_level == 4 in the records file;
  • raw AICore rows, raw AICPU rows and joined rows have equal counts;
  • for every timed task, joined physical rows == deps.block_num × active kernel_ids slots.

The last check is the one that matters most: a single dropped SPMD or MIX row turns a partial early-dispatch result into a false full N/N.

Distributed captures live under <work_dir>/dfx_outputs/rank{r}/d{k}/, where d{k} is that card's k-th L2 dispatch. Match the program by dispatch_program.json — two programs can reuse a func_id.

Reconstructing the critical path

python -m simpler_setup.tools.critical_path <work_dir> --stdout

It computes two paths, and the difference is the point:

  • Static CPM — the duration-weighted longest dependency path assuming unlimited cores. This is what the graph costs.
  • Observed — the as-executed backward blame path through data and same-core predecessors. This is what the run cost, and its task compute plus stalls tile the measured AICore makespan.

Use Observed to decide where time went; use Static CPM as a cross-check. A large gap between them is a scheduling problem, not a graph problem.

The makespan covers first AICore start through last AICore end — it excludes host and orchestrator front time and the AICPU tail. Level-4 collection has observer cost, so use it for causal evidence and take production numbers from an unprofiled benchmark; see Performance Tuning.

Tuning the schedule

Everything above describes the machine. This section is the method: a loop that turns a level-4 capture into a shorter schedule, one question at a time.

1. find the Observed critical path        ── only its tasks can shorten the makespan
2. split every gap on that path           ── FIN detect | undispatched | pickup
3. flag the producers of a gapped task    ── allow_early_resolve=True on each one
4. prove the task was actually staged     ── dispatch < producer FIN, per block
5. if a sibling took the window, evict it ── unflagged dummy on the SIBLING
6. re-measure, and re-derive the path     ── it moves once the head shortens

1. Find the path. Reconstruct the Observed critical path from the capture (see Reconstructing the critical path). Only tasks on that path can shorten the makespan; time spent on anything else is slack until the path itself moves.

2. Split every gap on the path. A gap is not one thing — it is producer-FIN detection, ready-but-undispatched scheduler delay, or post-dispatch pickup, and each has a different remedy. The taxonomy below does the splitting.

3. Flag the producers. The undispatched and pickup parts of a gap in front of a short task are what speculative early dispatch removes. Flag every direct producer of that task — all of them, because one unflagged producer disables the whole opportunity.

4. Prove the window was actually won. A flag in the source is not a result. Check the dispatch timestamp against the producers' FIN, per physical block, and accept full, partial or none as the answer.

5. If a sibling took the window, evict it. When the path task is structurally eligible yet still not staged, look at what else shares its producer. Normal work outranks early work and the early lane is serviced only once both normal lanes are empty, so a non-critical sibling resolving off the same producer can consume the opportunity first:

c ──► a     on the critical path — wants the early window
└──► b      not on the path — currently taking it

Adding an unflagged dummy predecessor to b makes b structurally ineligible and leaves the window to a. Add it to b only — never to a, and never to the shared producer c, which would delay both.

6. Re-measure, then re-derive the path. Shortening the head of a path usually moves the path. Judge the change on wall time from an unprofiled benchmark, not on the level-4 capture that has observer cost built in, and not on core busy time.

The rest of this section is the reference for steps 2 through 5.

Reading the gaps

Split the interval before a task into three causes, because each has a different fix:

Interval Name Meaning
producer end → producer finish FIN detection The scheduler had not yet noticed the producer finished
last producer finish → dispatch Ready-but-undispatched The task was legal to run and no core took it
dispatch → start Pickup / gate The core had not yet picked it up, or the task is early-staged and still gated

With these four values folded across every physical block of a task:

data_ready(C)     = max(pred.end_time_us)
observed_ready(C) = max(pred.finish_time_us)
dispatch(C)       = min(C block dispatch_time_us)
start(C)          = min(C block start_time_us)

Attribution rules that keep a gap analysis honest:

  • A ready-but-undispatched gap is a scheduler or occupancy claim, and naming a blocking task requires proving that every compatible core lacked a free slot throughout the interval — not merely that some other task overlapped it. Level-4 scheduler phase records carry counts, not causal task IDs; temporal proximity is not causality.
  • A pickup gap can be same-core contention, but only if the occupying task ran until start(C). A task that freed the core before data_ready(C) did not gate anything.
  • dispatch(C) < observed_ready(C) means the task was dispatched before its producers finished. That is not a paradox — it is speculative early dispatch, and the remaining wait is a gate, not a queue.

Speculative early dispatch

The one lever that removes the ready-but-undispatched and pickup gaps together. The scheduler may pre-stage a not-yet-released task onto an idle core, gated, and release it with a doorbell the instant its producers finish. The core is already holding the payload, so pickup latency is off the critical path.

It is enabled by a producer-side hint:

with pl.spmd(token_tiles, name_hint="rms_norm", allow_early_resolve=True) as rms_tid:
    ...

allow_early_resolve=True is accepted by pl.at, pl.spmd, pl.submit and pl.spmd_submit. It is pure scheduling — results are unaffected.

Four conditions decide whether it does anything:

  1. Every direct producer of the consumer must be flagged or already complete. Flagging one producer of a three-producer consumer buys nothing. This is why the hint tends to be applied along a whole chain, as in models/qwen3_14b/decode_fwd.py.
  2. A producer propagates eligibility only once fully published — published_block_count == logical_block_num. A 50-block SPMD producer on 24 cores dispatches in waves, and a consumer that gated every slot after the first wave would strand the remaining producer blocks. Full publication is the deadlock guard.
  3. Normal work outranks early work. Under a saturated engine there is no early window to win.
  4. A predicated task never early-dispatches, and a sync_start cohort needs all-or-nothing capacity.

Proving a task was actually early-dispatched

deps.json::tasks[].early_dispatch is not proof. It records that the task carries the producer-side flag — a statement about that task's consumers, not about the task itself. Two things must hold together:

structural:  every direct producer is an allocation source or has early_dispatch=true,
             and at least one is a non-allocation task
temporal:    block.dispatch_time_us + tol < max(producer finish_time_us)
             where tol = 2 * 1e6 / metadata.clock_freq_hz   (two clock ticks)

An SPMD task can satisfy this on some physical rows and not others, so the honest answer is full N/N, partial N/M, or none — never a bare yes. If the timestamps look early but the graph is not structurally eligible, the capture and the source disagree; suspect a stale artifact before believing the timestamps.

Deliberately delaying a task

pl.system.task_dummy has uses beyond joining producers, because a task with no work still costs one dispatch hop. Three idioms appear in this tree, and they are easy to confuse:

# 1. Join: collapse several producers into one handle.
gate = pl.system.task_dummy(deps=[tid_a, tid_b])

# 2. Delay by one hop: a real producer, plus a hop, before a non-critical
#    consumer — so it stops resolving at the same instant as the critical one.
#    decode_swa() in models/deepseek_v4_flash_dspark/decode_swa.py
late_dep = pl.system.task_dummy(deps=[rms_tid])
qkv_proj_rope(..., late_dep)

# 3. Placeholder: a standalone entry has no fused-path producer to fence
#    against, so an empty dummy satisfies the shared signature and is ready on
#    submit.  indexer_test() in
#    models/deepseek_v4_flash_dspark/decode_indexer.py
late_dep = pl.system.task_dummy(deps=[])

Form 2 is the deliberate one. Its comment in decode_swa.py states the intent plainly — "Dispatch barrier: kv_proj_matmul resolves one hop after rms_norm" — and it costs a dispatch to buy the ordering.

The fourth form is step 5 of the loop: an unflagged dummy predecessor makes its consumer structurally ineligible for early dispatch — it breaks condition 1 above — which is how a non-critical sibling is pushed out of a speculative window a critical-path task needs. No model in this tree currently ships one, because it is a scheduling experiment rather than a structural requirement: it is defensible only with before/after level-4 evidence that the sibling stopped being staged and the protected task started, plus a wall-time result. Keep deps= empty — task_dummy(deps=[c_tid]) adds a real hop after c and tests something else entirely.

task_dummy accepts only deps=; it cannot itself carry allow_early_resolve. All of these trade throughput for ordering, none changes results, and none is justified without a before/after measurement.

Traps this repository has hit

Each of these produced wrong results, not a diagnostic.

WAR through two views of one tensor. Tracking keys on the tensor value, so two distinct pl.reshape views of the same external inout tensor look independent. A task reading through one view and a later task writing in place through the other get no edge, and the write races the read. Seen on the decode KV-cache writeback: kv_cache validated clean while x_out failed around 7% with non-deterministic indices — the signature of a race, not of a numerics bug. The live fix is a no-op self-copy that marks the parameter inout before the gather, so the writeback takes a WAW edge on it; add_inout is a param-level property, so one tile touch is enough. See the kv_touch scope in models/deepseek_v4_pro/decode_sparse_attn.py and its siblings in the _csa variants.

A GM round-trip registered as add_output. A GM tensor written by one task and read by a later one must be registered on the producing task as add_inout, not add_output. add_output records only the write, so the consumer's read-after-write edge never exists. A clean A/B on decode_compressor_ratio4.py gave 20/20 passes with add_inout and 16/20 with add_output, the failures splitting between wrong values and a 507046 AICPU sync timeout. Worth knowing when reading generated orchestration under build_output/<case>/orchestration/.

A manual_dep=True tensor rides only on the explicit chain. Its ordering comes from deps= and nothing else, for the tensor's whole lifetime. Removing one deps=[tid] to re-anchor a wait silently dropped the only edge ordering a cumsum before its consumer — no compile error, stale reads. The restored form is visible as the two-element dependency on the dispatch_gather scope of models/deepseek_v4_flash_dspark/moe.py. Before cutting an explicit edge, check whether any task it transitively orders reads a manual_dep tensor.

A conservative overlap that was not a dependency. A pl.range loop whose iterations write disjoint slices of one output serializes on a WAW chain. The opt-outs fix it by assertion; slicing the output in orchestration so each task receives a distinct region fixes it by construction, at the cost of more orchestration tensors to register and walk. On a dispatch-bound graph that cost can exceed the serialization it removed — measure both ends.

See also

Upstream references: